Abstract

An aggregate scheduling problem for a flexible manufacturing system which consists of a machining and an assembly subsystem is presented. The aggregate schedule developed is used as an input to a real-time scheduling problem discussed previously by the author. Although features of the flexible manufacturing environment are not explicit at the aggregate scheduling level, they are incorporated at the real-time scheduling level. The single-product and N-product scheduling problems are considered. To solve the problems two optimal scheduling algorithms are developed. Each algorithm is illustrated with a numerical example. The results are also applicable to the single-batch and N-batch scheduling problems.

Keywords

Sustainability

Published Article/Book Citation

IEEE Transactions on Robotics and Automation, 5:4 (1989) pp.451-459.

This document is currently not available here.

Share

COinS
 

URL

https://ir.uiowa.edu/mie_pubs/10